线路单杆塔基础分坑的新方法
摘要::送电线路的分坑测量工作,是复测分坑工作的一项重要内容,分坑测量不仅要准确无误的做好坑口放样工作,而且要充分考虑到分坑放样后的开挖、下盘、浇筑等工作的质量控制和检查,本文对通常的施工方法对单杆塔基础在分坑过程中存在的问题作了分析,并根据存在问题的原因进行了改进,改进后的方法经实践证明不仅操作简单、使用方便而且为以后的基础开挖和浇筑等工作的检查和控制奠定了基础,充分体现出上道工序为下道工序服务的思想理念。
关键词:单杆塔基础分坑控制检查
new method to pit allocation of electric line single tower base
li yan, liu zhiwen peng gang
(luoyang power supplpany, luoyang 471000,henan china)
abstract:pit allocation measurement of power transmission line is a important content for resurvey measurement and pits allocation. resurvey measurement and pits allocation do not only require accurate pit laying off, but also need to consider quality control and inspection of the digging, footwall, concreting after pit allocation laying off. this article analyzed the problems of pit allocating single tower under normal construction method, and enhanced the method according to causes of existing problems. enhanced method is not only simpl
e and convenient, but also lays a strong foundation for quality control and inspection of basic digging and concreting which express the idea that first working procedure serves the next working procedure.
key word:single tower base, pit allocation, control, inspection
0引言
单杆塔基础通常有钢筋混凝土电杆基础和铁塔基础,单杆塔基础分坑,按通常的施工方法操作比