贵州水泥厂3200D/T新型干法水泥生产线
节能技改项目
联合储库
人工挖孔桩施工方案
贵州建工集团第一建筑工程公司
2008年11月12日
目录
···············································03
2. 地质概况··············································03
·································04
·······························06
·································
08
6. 施工进度计划··········································08
·····································09
········································09
··········································11
····································
13
11、附录(安全文明施工“具体操作要点”)······················15
1、工程概况
联合储库基础为人工挖孔桩,总桩数共132根,,桩顶标高为-,平均桩长自±,桩芯砼强度为C30,护壁砼强度参照《结构施工图统一说明》,钢筋为I,II级,桩端持力层为中风化白云岩层,。单桩竖向极限承载力设计值Q=6400KN。
主要工程量:土方工程量约1500立方米,护壁砼约450立方米,桩芯砼约1200立方米。
2、地质概况

根据外业勘探、测试及室内土工试验成果,场地勘探深度内各岩土层的岩性叙述如下:

①1杂填土:主要以杂色水泥硅质较正原料、碎石、砼块、少量粘土、砖块、生活垃圾组成,结构松散。~,,,场地可见率99%。
①2素填土:灰黄、黄色粘土、砂、碎石,具塑性,稍密~密实,底部偶见碎砖及煤渣,粗颗粒约占25~40%,均匀性差。~,, ,场地可见率46%。
②1 可塑红粘土:褐黄、黄绿色,可塑状态,块~致密结构,见少数裂隙发育,捻面光滑细腻,塑性高,中等压缩性。~,,,场地可见率60%。
②2 软塑红粘土:褐黄、黄绿色,软塑状态,致密结构,捻面光滑细腻,塑性高,下部见原岩残块。~,,,场地可见率45%。分布在场地的低洼处和溶沟、溶槽及溶洞裂隙中。
③1强风化白云岩:浅灰、灰白色,碎裂结构。岩芯呈砂~碎块状、块状和碎石夹粘土,性脆,风化裂隙发育,~,,,场地可见率93%。
③2 中风化白云岩:灰、灰白色,薄~中厚层,块~层状结构,夹少数泥质白云岩和泥岩。岩芯为短柱状、柱状和块状,采取率低(55~88%不等),~,,,场地可见率100%。
3、主要施工方法及技术措施

严格按照《结构施工图统一说明》中的要求进行施工。
桩底宜挖成锅底形,锅底中心比四周低200mm,根据试验,它比平底桩可提高承载20%以上。
桩底应支撑在可靠的持力层(密实卵石层)上,桩全长配置钢筋;箍筋采用螺旋箍筋,间距为φ******@100mm;为加强钢筋笼的刚度和整体性,每隔2m设一道φ16mm焊接加强筋;钢筋笼长超过10m需分段拼接,拼接处应用焊接。

:场地整平→放线、定桩位→挖第一节桩孔土方
→支模浇筑第一节混凝土护壁→在护壁上二次投测标高及桩位十字轴线→安装垂直运输架、封闭吊土桶等→第二节桩身挖土→清理桩孔四壁、校核桩孔垂直度和直径→拆上节模板,支第二节模板,浇筑第二节混凝土护壁→重复第二节挖土、支模、浇筑混凝土护壁工序,循环作业直至设计深度→检查持力层后进行扩底→清理虚土、排除积水、检查尺寸和持力层→吊放钢筋笼就位→浇筑桩身混凝土。当桩孔不设支护和不扩底时,则无此两道工序。
在施工过程中,根据实际情况