Contents
目录
piling basis and principle
编制依据和原则
Two Project in brief
工程概况
anization chart and specific schedule
施工组织结构和具体进度计划
Four Method statement and preparation
施工方案及施工准备
Five Main construction method and workmanship
主要施工方法及施工工艺
Six QA measures
质量保证措施
Seven Construction schedule
施工进度计划表
Eight QC measures
质量管理措施
Nine HSE measures
HSE 措施
piling basis and principle
编制依据和原则
Compiling basis
编制依据
Construction blueprints and pertinent information furnished
塞拉尼斯(南京)乳液项目提供的施工蓝图及相关资料(1045-860)
Drawing collection for water supply and drainage (volume 2004)
《给水排水标准图集》合订本(2004版) (GB50160-92)
Technical specification for polyethylene wrapping layer for steel pipe
《钢质管道聚乙烯胶粘带防腐层技术标准》(SY/T0414-98)
Construction and acceptance codes for water supply and drainage works
《给水排水工程施工及验收规范》(GB50268-97)
Construction and acceptance codes for industrial metal piping
《工业金属管道工程施工及验收规范》(GB50235-97)
Work and acceptance codes for welding of onsite industrial piping
《现场设备工业管道焊接施工及验收规范》(GB50236-98)
Surveying codes
《工程测量规范》(GB50026-93)
Checking and evaluating of concrete strength
《混凝土强度检验评定标准》(GBJ107-87)
Compiling principle
编制原则
Adoption of advanced technical and workmanship, efficient equipment together with scientific management to achieve pletion of the project;
采用先进的施工技术、工艺,选择高效的施工设备,科学组织,严格管理,确保工程目标。
Fully understand the drawing to develop a practical method statement;
充分理解设计图纸,编制可行的施工方案。
Schedule the project efficiently and rationally; divide it scientifically to meet actual situation on site.
进度安排高效、合理,施工区段划分科学,符合施工现场实际情况。
Two Project in brief
工程概况
Project in brief
工程简介
Systems included: RW, FW, PW, RAW, WW, CWS, CWR, SW and all other underground piping; wells in this project are all made of concrete or brick.
整个厂区内系统:包括RW(雨水管)FW(消防给水管)、PW(生活水给水管)、RAW(生产给水管)WW(生活污水管)、CWS、CWR(循环水管)、SW(生产废水管)在内的所有埋地管线。本工程井为混凝土井和砖砌井。
Pipe material
管道材料
Material for pressure pipe