目 录
编制依据编制原则········································3
工程概况················································3
分部分项工程施工方案与技术措施··························4
质量通病及防控措施······································20
质量保证措施和创优计划··································29
施工总进度计划及保证措施································31
施工安全措施计划········································32
文明施工措施计划及标准化工地实施方案····················33
各工序的协调措施········································36
赶工措施保证体系········································36
保证工期措施··········································38
施工场地治安保卫管理计划······························39
施工环保措施计划······································40
季节性施工方案········································40
施工总平面布置图及施工流水组织························41
项目组织管理机构······································
42
成品保护和工程保修工作的管理措施和承诺················44
紧急情况的处理措施、预案以及抵抗风险的措施············45
与建设单位、监理单位、设计单位的配合··················47
附表一、拟投入本工程的主要施工设备表························49
附表二、拟配备本工程的试验和检测仪器设备表··················50
附表三、劳动力计划表········································51
附表四、工程进度横道图······································52
附表五、施工总平面图········································53
附表六、临时用地表··········································54
(一)、施工测量准备工作
1.图纸审核:会同技术人员对图中大样尺寸进行校核,确保工程整体尺寸吻合无误,以便施工顺利进行,如有疑义直接同监理、设计洽商。
2.班组建立:设测量队长1人,主测2人,测工2人。
3.仪器、用具的配备及检定情况
4.以业主单位提供的现场点位及书面成果为定线依据。接桩后,立即对所接点位进行复核(包括书面资料数据计算复核、现场桩位实测坐标高程值与资料数值的复核)。将复核结果整理成书面材料上报监理,差值大于规范要求的,应再次复查,若情况属实,则在征得监理及业主同意的情况下,修正数值或将其作废。核对完毕,根据现场情况砌池护桩,并引出附桩,做好附桩图,以便日后桩点破坏的再恢复。
5.控制点加密:本段全线面积较大,故不宜采用单个的控制方法,为保证全线道统一,拟定采用城市二级附合导线做平面控制,每边平均边长设为200m,点位要求在路两侧交错埋设。内业计算使用计算机,采用工程附合导线近似平差程序,结果打印并保存。
6.高程控制点加密:在施工区线路两侧每隔100m均匀布设施工水准点,采用四等附合水准方法。
(二)、施工测量放线
1.平面定位:平面定位采用极坐标测设,应用计算机先计算出各桩位、桩点坐标以及放线数据,打印成书面表格形式。内业计算校核无误后,在现场将经纬仪置于加密控制点上,进行测放。放线完毕立即进行校核,用钢尺拉出和桩点的间距,同坐标反算之距离值比较,以此方法可校验同次放线各桩点之间的相对位置关系,不合格者立即复查并重放直至合格。平面相对关系校核完毕后,将全站仪置于另一加密控制点,实测桩点中相距最远的两点坐标,同设