This method statementis to describe the procedure and techniques of construction of traffic diversionroads in a safe manner that will satisfy all the requirements.
Section : Scope of Work
This method statement describes the activities related totraffic diversion roads, including site clearance(REF:E*W-P011-0000-CM-CHE-MT-00002), embankment(REF:E*W-P011-0000-CM-CHE-MT-00011、E*W-P011-0000-CM-CHE-MT-00006), sub-grade(REF:E*W-P011-0000-CM-CHE-MT-00011、E*W-P011-0000-CM-CHE-MT-00006), road base(REF:E*W-P011-0000-CM-CHE-MT-00025), asphalt work, installation of pole light(REF:E*W-P011-0000-CM-CHE-MT-00085), traffic signal(REF:E*W-P011-0000-CM-CHE-MT-00096), installation of sign board, safety barriersand road marking etc. These activities are covered in separated method statement.
Section : Responsibilities
The work will be carried out by CHEC, headed by the Construction Manager.
Construction Manager–Partially responsible for the construction and arrangement of civil works,in charge of site engineer.
HSE Engineer & HSE Officer–Responsible for HSE on site during construction, coordinate with Site Engineer, infrastructure superintendent.
QC Engineer–Responsible for quality of structure on site during construction, coordinate with Site Engineer, request for Inspection and Testing processes and coordination with the Engineer’s Inspectors representative.
Surveyor–Responsible for survey work and settlement monitoring work on site, coordinate with Site Engineer, the survey request process and coordination with the Engineer’s surveyor representative.
Site Engineer –Site engineer responsible for construction of work, coordinate with HSE Engineer, QA/QC engineer, surveyor, will in charge of foremen, operators, drivers, labours, reports