Method Statement
Document Title:
Construction of Traffic Diversion Roads
Document No.:
EXW—P011-0000-C0-CM-CHE—MT-00011、EXW—P011-0000-CM—CHE—MT—00006), sub—grade(REF:EXW-P011—0000-CM—CHE—MT-00011、EXW-P011—0000-CM—CHE—MT—00006), road base(REF:EXW-P011—0000—CM-CHE-MT—00025), asphalt work, installation of pole light(REF:EXW-P011-0000—CM—CHE—MT—00085), traffic signal(REF:EXW-P011—0000-CM-CHE—MT—00096), installation of sign board, safety barriers and road marking etc. These activities are covered in separated method statement.
Section 3。0: Responsibilities
The work will be carried out by CHEC, headed by the Construction Manager.
Construction Manager – Partially responsible for the construction and arrangement of civil works, in charge of site engineer.
HSE Engineer & HSE Officer – Responsible for HSE on site during construction, coordinate with Site Engineer, infrastructure superintendent.
QC Engineer – Responsible for quality of structure on site during construction, coordinate with Site Engineer, request for Inspection and Testing processes and coordination with the Engineer’s Inspectors representative.
Surveyor – Responsible for survey work and settlement monitoring work on site, coordinate with Site Engineer, the survey request process and coordination with the Engineer's surveyor representative.
3 / 49
Site Engineer –Site engineer responsible for construction of work, coordinate with HSE Engineer, QA/QC engineer, surveyor, will in charge of foremen, operators, drivers, labours, reports directly to construction manager, request for Inspection and Testing processes and coordination with the Engineer’s Inspectors representative, as well as supervisor.
Foreman—Directly supervises the work activity on the site and has full control over the use of the labour, plant and equipment. He ensures that the work is carried out in full compliance with the specification, and in a manner that conforms to the safety requirements。 He reports to the Site Engi