INSPECTION OPERATION SHEET
IOS NO.
DESCRIPTION
XM-14-REV0
Mains Voltage Class I Lights
NO.
AQL
CLASS
INSPECTION/TEST
PARAMETER
MEAS
METHOD
SPECIAL INSTRUCTIONS
CONFROMANCE
YES
NO
N/A
1
0
Critical
Mains Plug
Check for correct symbols and their authenticity. Check if there is foreign metal object within the plug.
Visual
Premier Specification: PD/303 and BS 1363.
This check to be reported as found on FRI report.
2
0
Critical
Pull test for terminals:
20 N for 1 min. Terminal should not detach fm the wire.
Visual/
Physical
EN 60598-1
3
0
Critical
Check cable anchorage by pulling the wires with 60N (round 6kg weight), 25 times, 1 S each time. The wire movement should not exceed 2mm.
Visual/
Physical
Premier Specification No. PD/303.
EN60598-1
4
Major
Check 10% of sample for the following:
a) Open plug and check for correct wiring.
b) Ensure no strands protrude out of terminals and that both terminals are screwed tightly onto the wire.
c) Ensure terminals are not soldered.
Visual
Premier Specification No. PD/303
5
0
Critical
Check for correct fuse (3 Amp) and it’s authenticity.
Visual
Fuse to meet BS specification BS 1362
6
0
Critical
Security of Bulbholders
Check for Premier approved bulb and bulb holder against Premier Product Specification Sheet.
Check 10% of sample size to ensure bulb glass does n
欧规灯具检验标准[1] 来自淘豆网m.daumloan.com转载请标明出处.