银盘水电站一期工程过水土石围堰防冲设计及应用
摘要:重庆银盘水电站右岸一期工程中后期过水土石围堰设计中,结合一期工程的导流特点,充分利用过水土石围堰上下游水位差低的实际情况,对过水土石围堰断面和防冲设计,并成功应用于实际工程。
关键词:银盘水电站土石围堰防冲设计及应用
中图分类号:S611文献标识码: A
The overflow earth-rock cofferdam scour protection design and Application of the first phase of Yinpan hydropower station
YuFuhai
Datang (Yunnan) United Hydropower Developing CO.,LtdYunnanKunming
Abstract: The overflow earth-rock cofferdam scour protection design,in the middle and later periods of the first phase of Chongqing Yinpan hydropower station right bined with the characteristics of diversion, makes full use of the actual situation of the low water-head between upstream and downstream of the overflow earth-rock cofferdam,to design for the section of the overflow earth-rock cofferdamand scour protection and make it to the practical engineering.
Keywords:Yinpan hydropower stationearth-rock cofferdamerosion protection design and application

1概述
重庆银盘水电站右岸一期工程施工导流采用原河道导流,上下游土石围堰方案进行施工明渠开挖和纵向围堰碾压混凝土施工。施工期间,根据工程特点和实际进度情况,将原设计的中后期的上下游3年一遇全年挡水围堰,调整为仅留上游枯期围堰作为纵向围堰碾压混凝土施工通道,即过水土石围堰,下游围堰汛前拆除,基坑进水的方案。该过水土石围堰不作防渗处理,仅进行断面及防冲设计,经受住2007年汛期过流考验。本文就该过水土石围堰设计研究及总结。
2过水土石围堰要求
过水土石围堰形成后主要保证纵向围堰碾压混凝土正常施工通道,为此,要求确保安全度汛和纵向围堰砼汛期正常施工,并满足设备物资转移的运输要求。
3过水土石围堰堰址条件
过水土石围堰主要利用原上游枯期围堰加高填筑而成,该部位现场实际顶部高程从右向左为EL193m~EL190m高程,与乌江主河道夹角为69°,迎水面主要为原河坡面,内为预留岩埂,预留岩埂一般在EL188m~EL192m,防冲性能较好,而位于混凝土纵向围堰堰头部位,内部预留岩埂高程为EL182m,EL18