Frequency conversion velocity
modulation hoist crane
变频调速起重机
Electrical fitting the servicing manual
电气安装使用维护手册
Establishes Zhao Guoqing
编制赵国庆
Shanghai Andun Hoisting Machinery Installation Co., Ltd
上海安顿起重机械安装有限公司
in December, 2008
2008年12月
第一章, 变频调速起重机的安装
The first chapter, frequency conversion velocity modulation hoist crane's installment
1 电气设备的安装和调整
1 electrical equipment's installment and adjustment
起重机电气设备的安装Hoist crane electrical equipment's installment(包括电机、电控设备、元器件、电线电缆的安装、敷设Including electrical machinery, electrically controlled equipment, primary device, electric wire electric cable's installment, placing)和调试With debugging(包括安装过程中的调整和电气设备安装后的通电试验等工作After the installation process the adjustment and electrical equipment installment work and so on circular telegram experiment)应按照随机提供的电气系统图Should defer to the electrical diagram which provides stochastically、电路图、接线图(表)、电气布线图(管、缆图)Circuit diagram, wiring diagram (table), electrical wiring chart (tube, cable chart)、电气布置图、设备位置图、设备和元件安装图等图样和有关说明书所提出的要求进行Patterns and the related instruction booklet and so on electrical general arrangement, equipment site plan, equipment and part installation diagram proposed the request carries on。
进行安装调试工作前应详细阅读图样文件等资料,了解电气设备工作原理、安装调试注
意事项;详细列出安装调试工作的步骤、程序及安全措施;以便及时掌握及迅速处理安装调试工作中出现的技术和安全问题。Before carrying on the installation and trial run work, to read material in detail and so on pattern document, understood that the electrical equipment principle of work, the installation and trial run to pour the Italy item; Lists in detail installation and trial run work the step, the procedure and the security measure; In order to grasp and rapid processing promptly the technology which and security problem in the installation and trial run work appears
起重机电气设备的安装工作,须由具有安装许可证和营业执照的施工单位进行。The hoist crane electrical equipment's erection work, must by have installs the permit and the business license Construction carries on.
为确保安装调试工作的质量,应由熟练的电工与其它工种配合进行安装调试工作。
电气设备安