照明施工计划书南阳师范学院西区张衡教学楼吊扇采购与安装项目施工方案南阳市卧龙建筑工程有限责任公司 XX年04月12日目录第一章编制依据....................................................................................1第二章工程概述....................................................................................1第三章施工组织机构...........................................................................2第四章施工部署....................................................................................2第五章施工准备....................................................................................3第六章施工方法....................................................................................3第七章施工进度计划...........................................................................5第八章安装现场劳力计划...................................................................5第九章进入现场主要机具计划...........................................................6第十章施工质量保证措施...................................................................6第十一章施工安全保证措施...............................................................7第十二章文明施工管理措施.............................................................10 第一章编制依据 : 1)建筑电气工程施工质量验收规范(GB50303-XX)2)《建筑工程施工质量验收统一标准》GB50300-XX3)现场设备、管线焊接工程施工及验收规范GB50236-984)电气装置安装工程电气设备交接试验标准GB50150-XX5)《施工现场临时用电安全技术规范》JGJ46-;–0630灯具、、工艺标准及工法。第二章工程概述 :::南阳师范学院西区张衡教学楼4总工期:: 为充分发挥企业优势,我们将选派高素质的项目经理及工程技术管理人员。按项目法施工管理,严格执行ISO9001质量保证体系,积极推广新技术、新工艺、新材料,精心组织,科学管理,优质高效地完成施工任务,严格履行合同,确保实现如下目标: 质量目标:合格工程。安全目标:严格按照国家安全文明施工的各项规定执行,工地现场实行禁烟、无垃圾管理,保持工完场清,市容环境卫生,按照国家标化管理。科技进步目标:为实现上述质量、工期、安全文明施工等目标,充分发挥科技的作用,在施工中积极采用成熟的科技成果和现代化管理技术。进度目标:坚守合同,确保安装总工期控制在15天之内。第三章施工组织机构根据本工程的实际情况,我公司将抽调富有施工经验、具有责任心的项目经理、施工负责人及技术负责人到现场进行管理,施工组织机构图如下: 第四章施工部署 (1)勘查:电扇安装标高及中心轴线。(2)现场接地极及防护是否到位。(1)分类选定材料堆放位置及加工区。(2)排定安装进度表及所需配属人力机具。(1)依安装计划、检查应到场施工机具准备。(2)电源、气源、应急医疗设备及消防器材配置。 (1)材料进场厂商应附材质检验证明或合格证。(2)检验扁钢及吊杆规格、尺寸、厚度及外观情况。(3)导线型号、截面积、电气性能。(4)检验零配件配置情况。(5)根据标准设立各材
照明施工计划书 来自淘豆网m.daumloan.com转载请标明出处.