Construction method statement for Steel Structure cleaning up and touch up
钢结构清理及补漆施工措施方法
A. Description 工作描述
This method statement is prepared for cleaning up the dust> scrap iron and rust iron remained on steel structure during transport before.
此方案主要是针对前期运输(海运)过程中残留在钢结构上的灰尘、铁屑、 铁锈等的清理工作制定的。
B. Manpower人员计划
The following is for one group and can be adjusted by adding manpower according to actual site condition when constructing.
Painter 4, mainly responsible for steel structure cleaning and painting .
Watcher 1, for preventing unauthorized people from entering.
以下人员为一个班组人员配置,施工时可以根据现场实际情况适当增加施工 人员及施工班组。
油漆工4人,主要负责钢结构清理及涂漆刷漆。
现场监护1人,主要监护非施工人员禁止进入。
C. Preparation 施工准备
1. To verify with each discipline if there are still constrution personnel enter into the area to be cleaned and the platform below it, to avoid working at the same time.
向各个专业确认即将清理的区域及清理区域的下…层平台是否还有施工 人员进入,尽量避免交叉作业。
2. Material: primer and top coat for steel structure, disc, nail.
材料准备:配备钢结构底漆及面漆、圆盘、尖头钉。
3. Tools: scissor lifts, ① 100 grinding machine, planning wheel, blower, roller(used by painter), inside grinding machine, inside grinding head, rag, safety belt.
工机具准备:剪刀式升降机、中100磨光机、刨光轮、压缩机、滚刷(油 漆工专用)、内磨机、破布、安全带。
D. Construction area defination and construction sequence 施工区域划
分及施工顺序
Principle for construction are