中海石油东营石化有限公司
7万吨/年常减压装置拆除
施工方案
工程名称: 7万吨/年常减压装置拆除工程
工程地点: 中海石油东营石化厂区
编制单位: 生产技术部
编 制:编制日期:年月日
审 核:审核日期:年月日
批 准:批准日期:年月日
目 录
一、工程概况······························································3
二、主要施工内容·························································3
三、编制依据······························································3
四、人员组织······························································3
五、施工要求·····························································4
六、施工进度表··························································5
七、拆除施工方式···············································
··········6
、施工方法····························································6
、设备、储罐及管道置换及清理·····································6
、管道拆除··························································6
、燃料油罐拆除·····················································6
、外保温的拆除·····················································6
、吊卸·······························································6
、现场清理··························································7
八、现场施工安全及防护措施·············································7
一、工程概况
根据中海石油炼化有限责任公司【海油炼化财[2013]268号】文件要求,中海石油东营石化有限公司决定于2014年3月对7万吨/年常减压装置进行拆除工作。
二、主要施工内容:
1、7万吨/年常减压装置管廊上部约930米工艺管