目录
第一章编制依据.................................................... 2
.......................................................... 2
........................................................ 2
第二章工程概况.................................................... 2
加固工程概况.................................................... 2
.................................................... 2
第三章施工部署.................................................... 2
........................................ 2
........................................................ 3
................................................ 3
、施工部署.............................................. 3
第四章施工准备..................................................... 4
........................................................ 4
.............................................. 4
第五章施工方案..................................................... 5
.................................................... 5
第六章安全文明施工................................................. 7
.................................................... 7
1
第一章编制依据
(1)昌平区老旧小区综合整治工程设计施工图纸
(2)招标文件和施工合同
《建筑施工高处作业安全技术规范》JGJ80
《北京市建筑工程施工安全操作规程》DBJ 01-62-2002
《施工现场安全防护、场容卫生及消防保卫标准》DB11/945-2012 《建筑施工手册第5 版》
第二章工程概况
加固工程概况
本工程为南环里小区住宅楼加固工程,位于北京市昌平区南环里小区内。为提高该居民楼抗震能力,减少能源消耗,遵循北京市人民政府要求对该居民楼进行抗震加固和节能改造。
需要加固的楼有:18#、19#、20#、21#、22#、23#楼。主体结构为砖混结构,建筑年代为80年以前,未进行过抗震加固,现对本工程不满足抗震鉴定标准的地方进行抗震加固。本工程采用外套抗震加固方法。
加固工程主体结构施工前,需要对原住户空调机、窗护栏、阳台、屋面等进行保护性拆除,做完装修后按设计要求恢复。结构施工时需要做现浇混凝土板墙、现浇剪力墙。
第三章施工部署
南环里小区加固工程结构施工前,需将原结构阳台或其他障碍物进行拆除。如无法拆除或发现结构存在问题时应及时向设计人员报告,待设计出处理措施、得到设计允许后方可施工。拆除施工要从实际出发,在确保人身和财产安全的前提下,选择经济、合理、扰民小的拆除方案,进行科学的组织,以实现安全、经济、速度快、扰民小的目标。
质量目标:拆除施工要保证不破坏楼体结构,楼体结构无伤害。 2
结合原住宅楼的实际情况、居民协调情况、施工中会遇到的重点和难点编制详细的施工方案和技术交底,对每一道工序的安排做到科学合理、高效紧凑、衔接紧密,在确保施工质量目标的前提下,为了