目录
1 编制依据······························································1
2 工程概况······························································2
3 施工部署······························································2


施工准备


4 主要项目施工方法····················································4
主要系统施工工艺流程


5 工程进度保证错施··················································5
制定图纸会审、图纸交底制度

6 工程资料管理措施··················································6
7 成品保护措施·················································· ······9
成品管理

8雨季施工措施··············································· ·· ····10
季节性施工的一般措施
雨季施工措施
9 施工安全保证措施··········································· ····11
1 编制依据
《北京华贸城五期小市政施工图纸》
《给水排水管道工程施工及验收规范》 GB50268-2008
《城市测量规范》 CJJ8-99
2 工程概况
本工程为北京华贸城中第五期工程,项目工程位于北京市朝阳区规划红军营西路、京包铁路、羊坊东路及规划清河营路围合路块。包括25#、25#楼市政工作、开发单位为北京华贸奥苑房地产开发有限公司,监理单位为北京赛瑞斯国际工程咨询有限公司,设计单位为北京市建筑设计研究院,施工总承包单位为青建集团股份公司。
3 施工部署

施工中以总进度计划为依据,按不同施工阶段、不同工种分解为不同的进度分目标,以分项管理、技术措施为保护手段,配合各专业施工,合理穿插作业,进行施工全过程的动态控制。


杜绝重大伤亡事故和重大设备事故;配合达到北京市建筑工程安全文明工地要求。

杜绝火灾事故和重大刑事案件。


施工前技术负责人、工长、质检人员必须提前到场,并组织有关人员对图纸进行认真会审,掌握图纸的设计意图,同时要做到及时发现问题,解决问题。将本专业与其他各专业有交叉施工的部位及有交接或联系的部分作为重点,进行详尽细致的校对和研究。

根据实际情况确定施工程序和施工方法,并根据施工图和施工合同,编制具有针对性和可操作性的技术交底。关键部位和特殊做法要绘出精细的大样图,以便工人高效完成施工任务。

为了保证施工质量和施工进度,同时减少浪费和降低成本,必须认真做好施工准备。作好进场前准备工作、施工现场准备工作、建立完善的计划保证体系。

主要机具的配备(见下表)
主要施工机具一览表

序号
名称
规格
数量
单位
备注
1
挖土机
2

良好
2
氧气
8

良好
3
乙炔
6

良好
4
试压泵
2

良好
5
电夯
380V
2

良好
6
震动棒
380V
2

良好
7
应急灯
220V
10

良好
8
电焊机
30KVA/380V
6

良好
9
热熔器
220V
4

良好
10
铲车
1

良好
11
切割机
380V
4

良好
12
污水泵
380V
2

良好
13
起重机
1

良好

劳务队伍准备:我们组织配合多年的工人队伍,具备很好的管理水平、施工技能和同类施工经验,做到操作人员持证上岗。为确保工程质量和工期,
劳动力计划安排表
第一阶段
第二阶段
土建
电焊工
水暖工
壮工
28