施工管井井点降水施工方案
目录
一、 编制依据··············································2
二、工程概况···············································2
三、施工准备···············································2
四、井点设置···············································3
五、工艺流程···············································3
六、操作要点及技术要求·····································3
七、质量要求···············································4
八、安全要求···············································5
九、环保措施···············································5
十、附井点平面布置图······································ 6
管井井点降水施工方案
一、编制依据:
《建筑工程施工质量验收统一标准》GB50300-2001
《建筑地基基础工 程施工质量验收规范》GB50202-2002
南长城·南湖国际一期13#楼工程施工图纸岩土工程勘察报告
及按建设单位要求,本工程采用管井井点降水,根据工程现场实际 情况及地质报告编制以下施工方案。
二、工程概况
南长城·南湖国际(一期)13#楼工程,位于贵州省印江县西环大桥以南。 m2,。该工程由商业裙楼及住宅组成。由贵州南长城企业(集团)房地产开发有限公司发包,上海经纬建筑规划设计研究院设计,湖南明泰项目管理有限公司监理,信息产业电子第十一设计研究院科技工程股份有限公司承建,结构类型为主楼二十五层剪力墙结构,裙楼为框架结构。
本工程场地复杂程度等级为二级;场地岩土种类较少,不均匀,性质变化较大,地基复杂程度为二级。根据对钻孔进行观测,~,与小溪沟水位相近,地下位随溪沟水位升降而升降,补给主要来源于小溪沟水渗入,其次是大气降水渗入补给。地下水的运动是通过卵石土层中的孔隙流向场地北边,在小溪沟低洼带以渗流形式排出。
三、施工准备
材料
φ225PVC管(滤管)、滤网、2~4mm
施工管井井点降水施工方案 来自淘豆网m.daumloan.com转载请标明出处.