驮英东干渠渡槽贝雷支架支模方案探讨
摘要:高空大跨度支模一直是建筑过程中存在的一个难点。广西左江治旱工程,为了解决渡槽高空大跨度施工问题,本文论证贝雷架在支模中的应用,对贝雷架支撑体系、受力分析、荷载验算进行分析,并在分析的结果上,对适用贝雷架进行选型。在渡槽施工中推广应用,工程中保证了结构质量、消除了许多安全隐患,降低施工成本、加快了施工进度,取得良好的应用效果。
Abstract:The high-altitude long-span formwork has always been a difficult point in the construction process, Drought Control Project in Zuojiang Guangxi,In order to solve the problem of crossing the high altitude and large cross construction site, this book The article demonstrates the application of the beret stand in the branch building,Analysis and load check calculation, and on the analysis of the junction ,apply the beret stand Make a is popularized and applied in the construction of aqueduct,and the quality of citrate is guaranteed ,Many safety hidden benefits are eliminated,construction costs are been reduced,and construction selection is accelerated ,Get good application results.
关键词:渡槽;贝雷架;计算选型
Keywords:aqueduct;beret stand;calculation and selection
一.概述
广西左江治旱驮英水库及灌区工程驮英东干渠标段有18座渡槽,槽身跨度为12m、15m和24m三种。槽身架空高度2米~。按比较常规的、常见的支模方案有满堂脚手架支模方案、钢管立柱+型钢支架支模方案,这两种方案工程中常见,施工技术较成熟,容易操作。缺点是费工费时费材,危险性较大。
现在我们探讨使用贝雷支架支模方案。贝雷支架是组装式的,工具性强,机械化施工程度高,可以大大减少人材机投入,保证了结构质量、消除了许多安全隐患,降低施工成本、加快工程进度[1]。
二. 钢管柱贝雷架支撑体系搭设
(1)结构设计:钢管柱贝雷架支撑体系是利用渡槽槽墩承台作为受力基础,内侧搭设钢管柱作为支承,然后通过工字钢横梁、贝雷梁、分配梁搭建形成组合支架[2]。见图1、图2。
图1 墩基础承台槽身支撑架立面图
图2 墩基础承台槽身支撑架剖面图
1)主要杆件尺寸
钢管:采用国标钢管直径219mm,,长度8000mm~22000mm不等;
横梁:国标45a工字钢,;
贝雷片:国产321型加强弦杆;,16Mn,单片重量270kg,尺寸3m××;
2)杆件连接和固定方式
钢管采用法兰盘连接,采用Φ18高强螺栓与排架柱固定;
贝雷片采用专用插销拼装接长,相邻两组贝雷片采用连接杆加固,与横梁接触面采用钢板限位,防止滑移和倾覆;
分配梁采用U型螺杆与贝雷梁连接固定,防止滑移和倾覆。
3)卸荷方式
贝雷梁支架体系采用50T机械千斤顶卸荷,50T机械千斤顶放置在钢管柱顶端中心位置,作为重要受力点承载上部荷载。
(2)搭设步骤
1)首先进行钢管柱的安装,钢管柱底座与承台采用膨胀螺栓固定,每隔3m与排架柱(薄壁墩)采用钢丝绳抱箍加固,防止偏移和倾覆。
2)钢管柱顶端放置50T千斤顶机,采用焊接限位钢板等方式将千斤顶机固定,防止偏移和倾覆;
3)50T机械千斤顶上部横向放置两根45a工字钢横梁,横梁采用抱箍与排架柱连接,防止横梁偏移和倾覆;
4)横梁上部纵向铺设9组贝雷梁(15m跨采用45
驮英东干渠渡槽贝雷支架支模方案探讨 来自淘豆网m.daumloan.com转载请标明出处.