第 1 页
曹妃甸工业区中日韩核心区路网工程
第二标段K0+0720+208污水施工方案
唐山慧鹏建筑有限公司
二零一六年
一、工程概况········································1
二、编制依据········································2
三、施工准备········································3
1、劳动准备·····································3
2、技术准备·····································4
3、机械准备·····································4
第 2 页
4、材料准备·····································5
四、施工方案内容····································6
五、施工方案········································7
1、测量放线·····································8
2、钢板桩施工···································8
3、开槽·········································9
4、排水·········································10
5、下管
第 3 页
·········································11
6、回填·········································12
7、检查井施工···································13
六、安全文明施工····································14
一、工程概况
中日五道西起西港路,东至北通大街,设计道路长1881米,道路宽度30米。本工程项目所处地表土层为新进围海造地而成,地势相对平坦,地面标高约为5米,地表20为新进吹填土,底下4m为淤泥沉淀层,地质条件复杂。
中日五道设计一道雨水管线,;管径7001400,分段排入西方路和北通大街以设计的雨水系统中。
布置一道污水管线,位于道路中心线南侧11米,管材为聚乙烯缠绕结构壁管材。管径400600,分段排入西港路和北通大街以设计的污水系统和规划北通西一街污水系统。
二、编制依据
第 4 页
《市政排水灌渠工程质量质量检验评定标准》、
《市政工程施工技术规范》、
《公路软土地基设计及施工技术规范》有关规定、相关依据
图纸相关要求,编制本施工方案。
三、施工准备
1、劳动准备
(1)我司将指派有丰富施工经验的项目经理按项目法模式组建现场项目部,实行项目法施工,由项目部全权负责工程管理工作,施工组织机构见下图
第 5 页
唐山慧鹏市政工程有限公司
项目经理部
项 目 经 理
李辉
项目副经理
赵广林
技术负责人
王朋如
工程技术部
质安部
材料设备部
计划财务部
办公室
施工技术
施工测量
工程试验
技术资料
材料设备管理体制
安全管理
材料设备维修
质量控制
文明施工
材料采购
经营计划
财务管理
成本核算
外部协调
人事劳资
后勤保卫
各施工作业区
交通疏解管理
具体人员配备见下图:
序号
人员职位
人员数量
备注
1
测量
4人
2
排水
6人
第 6 页
3
挖掘机司机
3人
4
打桩机司机
1人
5
铲车司机
1人
5
接管工人
4人
6
下管工人
6人
7
施工
2人
(2)工程部为日常施工指挥、调度中心,负责工程计划的编制和实施;机械调度;劳动力配制;协调项目经理部的施工进度。
(3)技术部是技术质量管理部门,负责工程日常的技术问题的处理;进行工程设计交底、施工技术交底制及工程质量事故和处理工作,指导项目经理部做好各环节的工序质量验收工作;指导和协调工程测量及工地试验室的工作;负责工程资料的收集、整理、存档。
(4)材料部负责工程材料的采购和管理;各类施工材料、成品、
中日五道雨污水方案 来自淘豆网m.daumloan.com转载请标明出处.