目录
第一章综合说明·······································1
第二章施工现场平面布置·······························3
第三章劳动力计划·····································3
第四章施工进度计划···································4
第五章施工进度施工工期保证措施·······················4
第六章主要施工机械、设备·····························5
第七章地下管线、地上设施、周围建筑物保护措施·········5
第八章主要施工方法或方案和施工措施···················6
第九章质量保证措施··································22
第十章各工序的协调措施······························24
第十一章冬、雨季施工措施······························24
第十二章施工安全保证措施······························24
第十三章现场文明施工措施······························26
第十四章施工现场环保措施······························27
第十五章施工现场维护措施······························27
第十六章与各协作单位配合服务承诺
······················28
第十七章工程交验后服务措施····························28
附表···················································30
第一章综合说明
1-1工程概况:
本工程为程盛道、跃进路、昆俞南路、规划一、规划二支路中水工程,工程地处东丽区,津塘公路南侧,外环线以内。
其中:程盛道中水工程,西起雪莲路,东至外环路,长约2210m,规划中线北侧拟建DN200~DN600mm中水管道,规划中线南侧拟建DN200~DN300mm中水管道;跃进路中水工程北起张贵庄路,南至山青道,长约1730m,拟建DN200~DN300mm中水管道;昆俞南路中水工程北起张贵庄路,南至山青道,长约1550m,拟建DN355mm中水管道;规划一支路中水工程西起规划二支路,东至昆俞南路,长约340m,拟建DN300mm中水管道;规划二支路中水工程北起规划一支路,南至山青道,长约330m,拟建DN300mm中水管道。
,。
1-2工程开工、竣工日期:
开工日期:2007年3月1日
竣工日期:2007年12月30日
共计304日历日
1-3编制依据:
程盛道、跃进路、昆俞南路、规划一、规划二支路中水工程招标文件;
程盛道、跃进路、昆俞南路、规划一、规划二支路中水工程中水管网施工图设计及变更设计通知书;
《给水用聚乙烯(PE)管材》(GB/T13663—2000);
《给水排水标准图集S5(一)》;
《水及燃气管道用球墨铸铁管、管件和附件》(GB/T 13295—2003);
《橡胶密封件、给水排水管及污水管道用接口密封圈材料规范》(HG/T 3091—2000);
《给水排水管道工程施工及验收规范》(GB 50268—97)。
我单位现有的施工技术能力、机械设备、施工管理水平及多年的施工经验。
1-4编制原则:
在施工组织设计的编制中始终按照技术可靠、措施得力、确保安全的原则确定施工方案。在安全措施落实到位,确保万无一失的前提下组织施工。
加强领导,强化管理,优质高效。根据我们在施工组织设计中明确的质量目标,积极推广、使用“四新”技术,确保创优规划和质量目标的实现。施工中强化标准化管理,严格控制成本,降低工程造价。
科学组织,合理安排,优化施工方案是工程施工管理的行动指南,在施工组织设计编制中,对工程的关键工序进行施工方案的研究制定,择优选用最佳方案。
根据工期要求,编制科学的、合理的、周密的施工方案,合理安排进度,实行网络计划控制,搞好工序衔、搭接,实施进度监控,确保实现工期目标,满足工期要求。
根据工程量大小及各项管理目标的要求,在施工组织上实行科学配置资源,合理安排劳动力。选派有施工经验