SAUDI KAYAN PETROCHEMICAL CO., LTD.
SAUDI KAYAN PLEX U & O PROJECT FLARE AREA
DOCUMENT TITLE:
METHOD STATEMENT FOR
INSTALLATION of ROTATING EQUIPMENT
Owner
CONTENTS
Scope 3
REFERENCES 3
GENERAL 4
PROCEDURE 4
Project HSE Plan 11
Attachments 11
SCOPE
The procedure is aimed to describe the rotating equipment, like pump, compressor, etc in Saudi Kayan U&O Project.
The installation should strictly follow all the applicable specification, standard, procedure (including HSE Plan), drawing and installation manual from vendor. If there is any conflict between this procedure and drawing requirement for the special requirement from equipment specification, the latter shall govern. At the same time, the procedure shall conform to the requirement from FLOUR .
REFERENCES
API 610
API 686
Plot plan
Installation manual
In which the installation procedures and allowable alignment tolerance can be found and referenced.
Vendor dwg
Drawings provided by the vendor and from which detailed fabrication drawings, assembly drawings, and sectional drawings can be found in order to ensure the mechanical assembly can be performed correctly
Piping arrangement dwg
From the drawings, the orientation and elevation of the equipment can be found.
Packing list
From which the quantity of each equipment part to be packed and more accurate weight can be found.
GENERAL
The inspection ply with relevant project specifications,drawings,manufacturer’s documents and applicable codes or local regulations.
Manufacture’s documents ,drawings and installation instructions will be used as a part of this procedure.
Equipment to be assembled at site,such as large pump will be installed in accordance with the installation instruction supplied by equipment manufactures and referenced documentation.
PROCEDURE
Work Flow for Construction of Rotating Equipment
PREPARATION
JOBSITE RECEIVING
FOUNDATIONS CHECK